Site Preparation Timeline
Begin site preparation at least 60 days before delivery. Late preparation is the most common cause of installation delays.
Foundation Requirements
8-color CI press weighs 18,000–25,000 kg. Floor requirements: 300mm reinforced concrete slab, 1,500 kg/m² load capacity, flatness ±5mm over 5-meter span, vibration isolation pads. LISHG provides foundation drawings during project planning phase.
Utilities
- Electrical: 3-phase dedicated supply, 80–150 kW total load, voltage fluctuation <±5%
- Compressed air: 6–8 bar, 500 L/min minimum, oil-free (ISO 8573-1 Class 1.4.2)
- Ventilation (solvent): Explosion-proof, 15–20 air changes/hour, Zone 2 ATEX rating
Commissioning Schedule
Day 1–3: Machine placement and leveling. Day 4–7: Mechanical and electrical connections, servo parameter configuration. Day 8–12: Software commissioning, register calibration, trial production run. Day 13–14: Operator training and handover documentation.